Tuesday, March 25, 2025

boat coat float soak

Yes, so a federal election has begun, here is what happened at the last election in my riding:

Given the big lead the Liberal had in 2021, it is highly likely he will win again, which is what my preference is.

The felon Cheeto Buffoon is having an impact on our election, one of the biggest election questions is which political leader is best suited to face up to the buffoon. The Liberal Party of Canada leader, Mark Carney, is who I see as being best at this.


Friday, March 14, 2025

Pi Pie pie pye

3.14159265358979323846264

In elementary school when I first learned about pi to calculate the circumference or area of a circle I generally stuck with 3.14.

Later on, I always used 3.14159. I felt that five decimal places was sufficient for the amount of accuracy that I would ever need.

Knowing pi to the twenty-third decimal places seems to me to be excessive and not particularly useful.

Wednesday, March 05, 2025

yep dep sep klept

So today is the day (well, yesterday since I started this post yesterday but didn't submit it until today), the felon Cheeto Buffoon starts the 25% tariff across all Canada and Mexico imports into the US with the exception of oil from Canada which is tariffed at 10%.

Canada introduced ~30B$ of retaliatory tariffs to take effect immediately. There is significant agreement among the politicians as to what to do, but I am uncertain if I agree to all of what is being suggested.

Retaliatory tariffs only have the impact of increasing prices of imports from the US here into Canada. Instead of doing that; simply stop buying as much as possible, US products. Already all of the alcohol stores across the country are removing or have already removed all US produced alcoholic drinks. An example of this, the LCBO is the biggest purchaser of Kentucky bourbon; so by stopping to buy this, will have an effect.

By having all levels of government do their procurement to the exclusion of US companies is another way to punish the American electorate for what their leader is doing.

Fortunately for me my job is in tech support to Canadian customers, so my job is not in jeopardy. I also have no major expense over the foreseeable future and so I will only see any increases in certain groceries. Others are not so fortunate with some job losses already having taken place; I hope that any funds raised during the retaliatory tariffs here in Canada can help those whose jobs are lost due to this fiasco. 

Tuesday, February 11, 2025

Well, then

A box, an isotope and a laundry hamper go water skiing. The driver of the boat with the engine that pulls them along had already drunk six servings of Jack Daniels and was in no condition to clearly monitors the water skiers he was dragging behind him. Fortunately, the box disintregated shortly, the isotope was not visibile and the landry hamper bounced around involuntarily but safely, so the driver didn't have anything to worry about until he crashed his boat into the pier at high speed.

Friday, February 07, 2025

that it wasn't

 sooo, if the sky isn't

when, that the floor

why, slouch the gruff

band - yep;

sloooooowwwww up? or is that kite?

Friday, January 24, 2025

breakfast cereal without telemetry

Amazon closing all warehouses and distribution centers in Quebec. This likely because one of the seven of them had workers who decided to become unionized and were in the process of negotiating their first contract. Now anyone in Quebec who orders Amazon will have to get trucked in from the nearest Ontario distribution center causing a lot more traffic from that location to various places across Quebec.

Trump more and more insistent on applying a 25% across the board tariff on Canadian goods going into the US. The latest update is that it could happen as soon as 1 Feb. I've been seeing news articles that this ought to jump start changes in Canada to allow for improved inter-provincial trade and to drive innovation to have more manufacturing here. Of course, the government here will put retaliatory tariffs on US imports into Canada, so some things here will become more expensive for consumers.

A saber toothed tiger and a nematode played speed chess together. The witnesses were amazed.

I had a dream this morning that I was making a really good choice. That's good. Of course, it would have been helpful if I could remember what the choice was.

The Canada Supreme Court decided to take on Quebec's Bill 21, which is a law the CAQ introduced that prohibits the wearing or religious symbols for public work jobs that face the public, so for teachers and nurses and so on. It is in essence a discriminatory xenophobic anti-Islamic law to prevent women who wear hijabs from being teachers. The CAQ is mostly propped up by rural and distant parts of the province who never see people like these Islamic women teachers, but in cities like Montreal, where I live, where the CAQ has no representation, there are a fair number and none of us Montrealais have any such prejudice (well, at least not in a majority). I hope the Supreme Court strikes down this law as a violation of the Charter of Rights and Freedoms.

Well, that is a short summary of what is going on at the moment.


Tuesday, January 07, 2025

Fifth anniversary

It was on this day five years ago that Neil Peart, drummer and lyricist of RUSH died after having suffered brain cancer for three years.

RUSH music definitely holds a place in my heart.

Wednesday, January 01, 2025

Thoracic Jurassic

Who would have guessed that this would be the very first day of a year that as a number is not a prime number?

I did not stay awake last night to witness the changing from the previous year to the current year; I was content to witness that as I awoke this morning.

My plans for this year are as yet vague, certainly for the first few months there is little that will change in terms of work, attending church regularly, having book group monthly, exercising regularly, writing blog posts and watching sports on TV.

I can still wish that for myself, and for the few readers of this blog, that we all have a pleasant next twelve months.

Wednesday, December 25, 2024

X cross

Get comfortable.

I watched this video over a year ago and this one more recently; both concern the idea of removing rail level crossings to improve the passenger rail traffic speed which can also raise the frequency.

So in the last day or so I had the idea of creating a company that does this. With the help of Chat GPT4.0 I got some refinements to my ideas and some answers to questions that troubled me about the idea.

The idea of the company is to have a majority of people on a salary, rather than on a per project, as there are hundreds of level crossings that need to be removed which could take 5+ years. Ideally we would get federal and provincial governments to kick in some of the funding, as well as the rail companies and municipalities.

In terms of staff we would have

  • a project manager who would treat each level crossing we remove as a separate project, to oversee each one that it sticks to budget and timeline and coordinates between the various teams and liaises with stakeholders (the federal and provincial governments for funding)
  • a geotechnical engineer to conduct soil testing and analysis to assess ground stability during excavation
  • a structural engineer that specializes in the design of both temporary and permanent structures and ensures compliance with safety standards and load requirements
  • an environmental consultant to assess environmental impacts and ensures compliance with environmental regulations, works with geotechnical engineer to plan for drainage systems
  • Safety officer to implement and enforce workplace safety standards and conducts safety audits and safety training sessions for all employees both onsite and at the factory
  • traffic management coordinator to develop and implement traffic management plans in coordination with the local municipality
  • Community engagement specialist to communicate with local residents and businesses to address concerns and keep them informed, to handle public relations and manage complaints
  • Rail operations coordinator to work directly with the rail company consultants to schedule rail closures to ensure minimal disruption
  • Heavy machine mechanic to keep all of our heavy machinery in good working order and do all required maintenance
  • Procurement specialist to manage the sourcing of supply of materials and equipment for both the factory and for on-site needs
  • Survey team - conducts initial and ongoing site surveys to guide excavation, structural placement and alignment
  • Crane and heavy equipment team to operate the cranes, hydraulic jacks and any heavy equipment
  • QA/QC team to inspect completed work to ensure it meets design specs and regulatory standards
  • Electric and Utility team to handle the relocation or adjustment of utilities
  • Drainage and Erosion control team to install drainage systems and stabilize surrounding terrain to prevent erosion
  • HR and Recruitment - to manage hiring, payroll, benefits and employee relations
  • IT specialist to maintain digital infrastructure including design software, project management tools, communication systems and anything else
  • Legal advisors to handle contracts, permits, regulatory compliance and advise on liability and risk management, to make contractual offers to rural land owners to close permanently any private level crossings
  • Insurance specialist to assess and arrange needed insurance for equipment, workers and liability coverage
  • Accountant to work out the accounting and reporting for the company
  • Rail Signal Specialists to advise on rail signaling adjustments during and after crossing removal including the removal of the crossing signals
  • Design consultants - assist with the adaptation of standard designs to unique site conditions and to provide 3D modeling and simulation as needed
  • General Workers - broken up into different teams:
    • Excavation team, with excavators, for any ground removal for example, doing an underpass under an elevated ground raised rail bed
    • Temporary structure team; to create, put in place and remove any temporary structures, for example, to support the rail bed using a temporary system to then allow for digging and then for permanent structural components to be installed beneath the rail bed
    • Construction team to put the new factory built permanent structural components into place
    • Road and ground finishing team to pave the new road section and do any ground scaping work once the actual new structure that removed the level cross is complete
    • Factory workers who build the standardized and non-standard structural components

Let us say that the very first level crossing we do is a pair of CN tracks that are flat and level with the surroundings. The project manager will have already enlisted funding from the different sources, 33% from the federal government, 33% from the provincial government and 34% from the rail company.

Then visiting the site will be:
  • The surveyor team to get all of the required measurements to develop a plan
  • the community engagement specialist will engage with the community around the level crossing,
  • the designer, structural engineer, environmental assessor, traffic management consultant and the rail consultant will develop the plan for a bridge to go over the train tracks
After formulating a site and project plan for the bridge that will go over the train tracks:
  1. The traffic management consultant and the project manager would coordinate with the local municipality to propose the level crossing project and to enlist their help to put in place a traffic management plan for the location, that the city will provide detour signs 
  2. The road gets closed
  3. The on-site office is placed, this is for the engineer, foremen and so on to have the plans, a desk and computer and anything needed
  4. the road and ground team move in to destroy the road that is immediately adject to the train tracks and works with the rail operations coordinator to remove the crossing signals and the pavement that exists between and around the train tracks, this would require a short rail traffic  unavailable window
  5. the construction team would install the standardized components that are delivered from the factory to put in the support structures on the North and South sides of the rail tracks and to create the up and down ramps on either side
  6. Working with the rail operations coordinator, the crane crew will install the pre-fabbed span pieces that connect the supports that are already in place on the N and S sides, this will require a 4-8 hour window of rail traffic unavailability
  7. The road and ground scape crew comes in to pave what is needed, ensure there is work done to manage drainage system and erosion control

The second level crossing removal we have is a pair of CP tracks on a raised ground elevated rail bed that is high enough that very little digging will need to be done beneath the tracks to have an appropriate height to pass beneath it. A slope up towards the crossing exists on both sides.

Once the traffic management consultant has finished developing and implementing the traffic management plan for the project 1 above, this consultant and the project manager can coordinate with the local municipality to propose this level crossing project and to enlist their help to put in place a traffic management plan for the location.

Once the site and project plan is done for project 1, the designer, structural engineer, environmental assessor, traffic management consultant and the rail consultant will develop the plans for the rail overpass that will now have the car and pedestrian traffic pass beneath. Some of these people will travel back and forth between project 1 and 2 as they are needed.

For project 2:
  1. The traffic plan developed will get put into place and the road gets closed on both sides of this ground elevated rail bed
  2. The excavation team will remove the slope material on both sides leaving and/or shoring up enough to keep the elevated rail beds sufficiently supported
  3. The temporary structure team will, with the help of the excavation team, excavate what is needed to put support posts and put in the temporary structure which is made up of four support beams, on the left and right side of both the N and S sides which have a span beam secured to them at the top as close to the rail bed as possible
  4. Dig near the rail bed as much as possible that can still maintain rail structural integrity in preparation for the rail traffic down time
  5. close rail traffic, raise gently and by a small amount the rails, dig out from beneath them, put supporting cross braces that rest on and are secured to the temporary span beams, lower the rails, inspect and test the rails, open rail traffic
  6. Fully excavate under the temporary structure, monitor frequently the temporary support structure to check for settlement or movement
  7. once crane team is done with project 1 that team can come to project 2 to help move into place the standardized prefabricated support posts on the left and right side and the new span that goes beneath the rail bed
  8. close rail traffic, raise gently and by a small amount the rails, remove the temporary support structure, and then lower the rails, inspect and test the rails, open rail traffic
  9. The road finishing and ground scaping team, once finished from project #1 can come to project #2 and pave the new road passing underneath the train tracks

So as each project phase is reached, releasing the consultants and teams, they can move on to the subsequent project. Conceivably the project manager and the traffic management consultant will always be three to five projects ahead so as to have scheduled work available to every team in quick succession. By doing this over and over, each of the teams will gain more experience and find ways to improve efficiency, both to lower the total project time, and more importantly, to lessen the duration that rail traffic is interrupted. As a goal we would want to have a project completion time that is well under what can be reasonably estimated. Another goal would be to have any level crossing removal site idle as little as possible. This might include having certain teams work overtime at specific times; for example, if it is a large excavation compared to normal we might bring in an additional excavator and work much longer shifts.

The factory would be located in an industrial zone to receive cement either already formed in the shapes and sizes we need, or, we fabricate them into our own standardized shapes. Similarly, we would receive steel and either fabricate what we need, or receive what we need and modify it slightly as needed. The factory will also have a distribution organization to ship out to work sites the various components as they are needed.

In some cases the level crossing comes at an angle to the rail tracks, where possible, we would alter the road to now go below or above the rails at a 90 degree angle so as to facilitate the construction and to continue to use standardized structural components.

We would do our best to schedule any rail traffic stop durations to be as short as possible and at times where it would be least impactful to rail traffic, which includes overnight work.

As we move from level crossing to level crossing, wherever there is excavation required, we would contract with local excavation companies to have their dump trucks come and pick up all of the excavated material. The actual excavators themselves we will move from site to site. In special cases the excavated material from a rail over pass can be used to build up the slope to a road overpass over rails at a subsequent cross level removal project site.

And finally, as mentioned earlier in the law section, there are some private level crossings out in rural areas that join a farmer's two parcels of land. We would devote funds to buy out farmers in cases like this to have land exchanges done such that the need for that crossing is eliminated. Similarly, in some cases where two level crossings within a small town exist very near to each other, we would remove one of them altogether since the other will no longer be a crossing, but a bridge or rail overpass that makes crossing always possible.

Tuesday, December 24, 2024

well then

If it wasn't for the door stop, the door wouldn't be stopped.

If it wasn't for the paper weight, the paper wouldn't be weighted.

That's about all I have to say today.

Wednesday, December 18, 2024

in keeping with the neighbours

A composite yuletide carol visited Carol. Carol received the composite yuletide carol with equanimity; she's received all manner of types of variations of carols. This includes carols concerning the left front armpit of a barn dog named 'Barry'.

That we are ever so gradually approaching the day that has the fewest number of daylight nano-seconds comes as no surprise to the author of this post. It would appear for at least half the year we are approaching just such a day.

In just a few short days we will begin the ever so gradual ascent to the day the the highest number of daylight nano-seconds.

Out of curiosity (thanks to Carol and her carols) I investigated the number of nanoseconds in the shortest day this year. There are 31,334,000,000,000 nanoseconds of daylight.